Building Needs Assessment Work Group Agenda
March 5, 2020 10:00 a.m. – 12:00 p.m.
SCLS Headquarters
Badger Room
Meeting Documents: https://www.scls.info/committees/building-needs-assessment-work-group/2019-12-19
To phone into a
meeting: 866-226-4650 (access code:
461-0318-2019 #)
10:00: Call to Order
10:02: Approval of previous
meeting minutes: February
6, 2020
10:05: Reports:
·
Attorney Input regarding BNAW process: Marty
10:10: Discussion:
·
Review the matrix updated with the RFI document
information.
RFI reports submitted by
design-build firms were sent to workgroup in advance of February meeting and
are saved on the shared drive in the February 2020 BNAW meeting folder and in
the BNAW main folder under Builder and Site Prospects.
1. Keller
2. Tri-North
3. Sullivan
4. Newcomb
5. Vogel Brothers
·
Develop numerical evaluation scale to use at the April
meeting to assess the builder information from presentations and RFIs that has
been compiled into the matrix.
11:45: Homework for
Next Meeting:
·
Add builder presentations information to the matrix
Timeline:
Feb
– April evaluation of RFIs & information from original presentations
and possible follow up with vendors
April
assign numerical evaluation with the goal of narrowing down the
list of vendors; develop reference questions, then call references before May
meeting
May Discuss
checked references
June
Site visits
July
Site visits
August
Decide on Design-Build vendor
Next Meeting Date: 4/2/20
at 10:00 a.m.
12:00: Adjournment
Parking Lot:
Need
to create:
·
Location report
·
Detailed design report
·
Mark and Vicki will look into items listed under Other “Master
Building Profile by Zones”
For safety concerns and needed protections. Do we have
Material Safety Sheets on these products which include necessary protections
and toxicity information?
·
SUN Expansion
·
Collaborative projects – continue to consider options
Members:
Corey
Baumann SCLS Delivery Services
Coordinator
Nan
Brien SCLS Board
Trustee
Kerrie
Goeden SCLS HR &
Finance Coordinator
Mark
Ibach SCLS Consulting
Services Coordinator
Jesse
Stewart SCLS Fleet Manager
Vicki
Teal SCLS Technology
Services Coordinator
Kristi
Williams SCLS
Board Trustee
Martha
Van Pelt SCLS Director